Concrete Slab Calculator: Estimate Yards, Bags, Cost & Gravel

Concrete Slab Calculator

Calculate exactly how many cubic yards, cubic meters, and pre-mixed bags of concrete you need for any slab. Includes built-in estimators for monolithic perimeter footings, sub-base gravel, 1:2:4 mix ratios, diagonal form squaring, and total installed cost.

Built by: Qudoos
Last Reviewed: October 22, 2026

Slab Dimensions & Specs

Common Slab Presets (Feet):

4″ is standard for patios and garages. Use 5″ to 6″ for heavy trucks or RVs.

2. Footings & Sub-Base (Optional)

Estimates 21AA / #57 crushed stone required (~1.4 tons per yd³).

3. Material & Cost Settings

$
$

Total Ready-Mix Concrete

5.43 yd³

Equals 4.15 m³ or 146.7 ft³ (includes 10% waste)

Pre-Mix Bags Needed: 245 bags (80 lb)
Total Slab Area: 400 sq ft
Diagonal Squaring Check: 28′ 3.4″
Estimated Slab Weight: 21,267 lbs (10.6 tons)
Gravel Sub-Base Needed: 6.9 tons (4.9 yd³)
1:2:4 On-Site Mix Equivalent (Dry Volume)
Cement (94lb) 33 bags
Sand 3.2 tons
Gravel 6.5 tons
Estimated Total Installed Cost
$3,415
Concrete: $815 Labor & Prep: $2,600

How to Calculate Concrete for a Slab

Whether you are pouring a 10×10 backyard shed pad, a 20×20 two-car garage floor, or a massive 30×40 pole barn foundation, ordering the exact amount of concrete is critical. Running short mid-pour creates a structural “cold joint,” while over-ordering wastes hundreds of dollars in unused ready-mix.

Our concrete slab calculator converts your 2D square footage and slab thickness into 3D volume—instantly outputting Cubic Yards (yd³) for US ready-mix trucks, Cubic Meters (m³) for UK, Australian, Canadian, and South African projects, and exact Pre-Mix Bag counts for DIY pours.

The Concrete Slab Formula

To calculate how much concrete you need for a slab manually, convert all measurements into feet, find the volume in cubic feet, and divide by 27 (since there are 27 cubic feet in 1 cubic yard):

  1. Find Square Footage (Area): Multiply Length (ft) × Width (ft). (Example: A 20 ft × 30 ft slab = 600 sq ft).
  2. Convert Slab Thickness to Feet: Divide your thickness in inches by 12. (Example: A standard 4-inch slab is 4 ÷ 12 = 0.333 ft).
  3. Calculate Cubic Feet: Multiply Area × Thickness in feet. (600 sq ft × 0.333 ft = 200 cubic feet).
  4. Convert to Cubic Yards: Divide Cubic Feet by 27. (200 ÷ 27 = 7.41 cubic yards).
  5. Add 10% Waste Allowance: Multiply by 1.10 to account for subgrade dips and form bowing. (7.41 × 1.10 = 8.15 cubic yards).

Common Concrete Slab Sizes: Yards, Bags & Cost Chart

Below is a quick-reference engineering table for the most popular residential and commercial slab dimensions, calculated at a standard 4-inch thickness with a 10% waste factor included:

Slab Size (ft) Area (Sq Ft) Concrete Needed (4″ w/ 10% Waste) 80 lb Bags Est. Installed Cost
10×10 Slab 100 sq ft 1.36 yd³ 62 Bags $850 – $1,150
10×12 Slab 120 sq ft 1.63 yd³ 74 Bags $1,000 – $1,350
12×12 Slab 144 sq ft 1.96 yd³ 88 Bags $1,200 – $1,600
20×20 Slab 400 sq ft 5.43 yd³ 245 Bags $3,200 – $4,200
20×30 Slab 600 sq ft 8.15 yd³ 367 Bags $4,800 – $6,300
24×30 Slab 720 sq ft 9.78 yd³ 440 Bags $5,800 – $7,600
30×40 Slab 1,200 sq ft 16.30 yd³ 734 Bags $9,600 – $12,800

1:2:4 Concrete Mix Ratio, Gravel Base & Form Squaring

1:2:4 Concrete Mix Calculator

If you are mixing raw aggregates on-site instead of ordering a truck, the standard 1:2:4 mix ratio uses 1 part Portland cement, 2 parts sand, and 4 parts crushed gravel. Accounting for the 1.54 dry-to-wet shrinkage conversion, 1 cubic yard of concrete requires roughly 6 bags (94 lb) of cement, 0.59 tons of sand, and 1.19 tons of gravel.

How to Square a Concrete Slab

Before pouring, you must verify your wooden form boards sit at perfect 90-degree angles. Using the Pythagorean theorem ($A^2 + B^2 = C^2$), measure diagonally from corner to corner. If both diagonal measurements match the Diagonal Squaring Check output in our calculator above, your slab forms are perfectly square.

Gravel Under a Concrete Slab

Never pour a slab directly on topsoil. Excavate and compact a 4-inch sub-base of crushed concrete (21AA) or #57 stone. This prevents frost heave, improves drainage, and stops the slab from cracking. Enable the gravel checkbox in our tool to see exact tonnage.

Frequently Asked Questions

How do you calculate how much concrete you need for a slab?

Multiply the slab’s Length (ft) × Width (ft) × Depth (ft) to get the volume in cubic feet, then divide by 27 to convert into cubic yards. For a standard 4-inch thick slab, convert 4 inches to 0.333 feet before multiplying, and always add 10% extra for waste and uneven subgrades.

How much does a 20×20 slab cost?

A 20×20 concrete slab (400 sq ft) poured 4 inches thick requires 5.43 cubic yards of concrete (including 10% waste). Just the ready-mix concrete costs around $750 to $900, while a fully installed 20×20 slab with grading, forms, rebar, and finishing labor typically costs between $3,200 and $4,200 ($8.00 to $10.50 per sq ft).

How much does a 24×30 slab cost?

A 24×30 concrete slab (720 sq ft) at 4 inches thick requires roughly 9.78 cubic yards of ready-mix concrete (about $1,400 to $1,650 for material alone). With professional excavation, compacted gravel sub-base, rebar reinforcement, and finishing labor, expect to pay between $5,800 and $7,600 total.

How many 80lb bags of concrete do I need for a 12×12 slab?

For a 12×12 slab (144 sq ft) poured 4 inches thick, the exact volume is 48 cubic feet. Since one 80 lb bag yields 0.60 cubic feet, you need 80 bags for exact volume, or 88 bags of 80 lb concrete when including a recommended 10% waste factor.

How much should I pay for a 10×10 concrete slab?

If you pour a 10×10 concrete slab (100 sq ft) yourself using 62 bags of 80 lb pre-mix concrete and basic 2×4 form boards, you will pay roughly $350 to $450 in materials. If you hire a professional concrete contractor, expect to pay between $850 and $1,150 due to minimum crew trip charges, base prep, and finishing labor.

Calculation Methodology

This calculator uses standard volumetric geometry ($V = L \times W \times D$), adding perimeter trench volumes when monolithic footings are enabled. Pre-mix bag counts adhere to ASTM C387 minimum yield standards (0.60 ft³ per 80 lb bag). The 1:2:4 mix breakdown applies a 1.54 dry-volume bulking factor, and slab weight assumes 145 lbs/ft³ for cured normal-weight concrete.

Read our complete Calculation Methodology →

Accuracy & Limitations

  • Subgrade Undulations: A 1/2-inch dip across a 20×30 slab consumes nearly 1 extra cubic yard of concrete. Always maintain a 10% waste factor.
  • Short-Load Penalties: Ready-mix orders under 4 cubic yards usually incur a $100 to $200 short-load delivery fee from local batch plants.
  • Disclaimer: Estimates are for material planning only and do not substitute for structural engineering or local building code requirements.

About the Author: Qudoos

Qudoos leads the technical development and methodology research for our suite of construction calculators. Calculator logic is rigorously tested against documented engineering formulas and reference standard cost estimating practices to ensure reliability for homeowners and contractors alike.

Found an issue with this calculator or its math? Report a correction.

Check Other Concrete Calculators: